Convention Centre and Tower Project

The Convention Centre and Tower Project in Doha, Qatar, features world-class architecture with a soaring 105-story tower and a spacious convention center. Encardio Rite provided geotechnical monitoring instruments for deep excavation works, including inclinometers, anchor bolt load cells, Jackout pressure cells, and sister bars, through Ammico Contracting Company. These instruments ensured the stability of diaphragm walls, secant pile walls, and ground anchors, providing critical data on lateral movement, ground stress, and groundwater levels, thereby ensuring safe and successful construction of this iconic structure.

Convention Centre and Tower Project

Nothing could better symbolize Qatar’s desire to create world-class architecture than the Doha Convention Centre and Tower, which would bring a truly futuristic aspect to the Doha skyline. The Tower soars 105 stories into the sky and offers panoramic city views from its prestigious central location on the Corniche. It would have 300 guest rooms, 80 serviced apartments, and 300 residential apartments. The Convention Centre, adjacent to the Tower, has 87,000 square meters of convention space and is destined to become an important regional and international exhibition location.

The project included ~ two three-level basements covering the full plot area. Thus, a proper retention system was necessary for deep excavation works, which comprised a diaphragm wall, a secant pile wall, and ground anchors. Excavation depth inside the retaining wall was up to -14 m. 

Instrumentation was specified for monitoring ground and wall movements, dewatering water control, and anchors. Inclinometers were used to monitor the horizontal deflection of the secant pile wall and diaphragm wall, which went 5 m below the toe level of the pile wall. Ground anchors were monitored with anchor bolt load cells, and groundwater with a piezometer

Encardio Rite supplied monitoring instruments through Ammico Contracting Company, which was awarded the contract for Enabling Works in 2008. The list of instruments used for the foundation works included:

  • Inclinometers (35 locations) were used to monitor lateral movement in-ground and in the diaphragm wall
  • Jackout pressure cells (10 sets) were used to monitor ground stress on the diaphragm wall
  • Anchor bolt load cells were used to monitor the load on anchors
  • Sister bars (70 no.) were used in the diaphragm walls to monitor stress
  • Open standpipe to monitor the groundwater level 
Project DetailsConvention Centre and Tower Project
LocationDoha, Qatar
Year2008